The Howell County Commission is clarifying the structural steps ahead for a proposed replacement facility for the county jail and sheriff's office, noting the project remains strictly in the early planning and evaluation stages.
Howell County Commissioner Ralph Riggs emphasized that the county has not requested construction bids for a new justice center or detention facility. Instead, the county has issued a Request for Qualifications (RFQ) to seek professional architectural services to evaluate future facility options.
Riggs explained that the procurement process adheres strictly to a Missouri law commonly known as the Mini Brooks Act, which is modeled after federal procurement regulations. Under this framework, architectural firms are evaluated based on specific qualification criteria rather than their fee structures.
"Firms are rated on specialized experience and technical competence in the design of law enforcement facilities," Riggs said, noting the criteria also include a firm's past record of cost control, work quality, ability to meet schedules and client references.
The commission expects to narrow the candidate pool to the top two or three candidates for formal interviews before selecting a final firm.
The next step will be for the chosen firm to conduct a comprehensive needs assessment to evaluate population size, security requirements, location options and structural size. The assessment will also generate preliminary cost estimates.
Following the needs assessment, the county will hire a financial consulting firm specializing in public projects to review projected tax revenues and funding capacity. The resulting analysis will determine what the county can realistically afford in terms of size and scope. It will also identify whether any local sales tax or capital improvement tax measures would be necessary to fund future construction and operations.
“The Howell County Commission remains committed to a thoughtful and clear planning process,” Riggs said. “Throughout this process the commission’s goal is to ensure that any proposed facility adequately meets the current and future needs of law enforcement, the courts, and public safety while being mindful of impacts to taxpayers.”
Riggs emphasized the project remains strictly in the planning and evaluation stage. No final decisions have been made regarding the type of project, structural size, overall cost or funding mechanism.
Riggs also noted commissioners appreciate the public’s interest in the project and will continue to provide updates on its progress.